The mouthful that was the
Housing Grants, Construction and Regeneration Act 1996, which thankfully became
more familiarly known amongst the many within and associated with the
Construction Sector as “the Act”, is due for amendment.
The Act had been due for
amendment by the equally, if not even greater mouthful, Local Democracy Economic
Development and Construction Act 2009, thankfully now quickly becoming known as
“the New Act”, but before the amendments can come into force changes need to be
made to the Scheme for Construction Contracts England and Wales 1998 (known as
“the Scheme”).
It had therefore, been expected
that the New Act would have come into force in April 2011; however, it does not
now appear that it will come into force until October 2011.
Nevertheless, what are the
important changes that the New Act will bring, when it does eventually come into
force? Part 8 of the New Act amends part 2 of the Act, both of which of course,
concern “construction contracts” as defined within the Act.
The New Act repeals s.107 of
the Act so that the payment and adjudication provisions of the Act shall apply
whether the construction contract is in writing or not.
The difficulty that may arise
is that it may be necessary to spend a disproportionate amount of time upon
arguments as to what are the contract terms compared to that upon the
substantive issue referred. Further, whilst a construction contract need not be
in writing, the adjudication provisions pertaining to the construction contract
must, otherwise the provisions of the Scheme shall apply.
The New Act inserts the following after s.108 of the Act:
“108A Adjudication costs: effectiveness of provision
(1) This section applies in relation to any
contractual provision made between the parties to a construction contract which
concerns the allocation as between those parties of costs relating to the
adjudication of a dispute arising under the construction contract.
(2) The contractual provision referred to in
subsection (1) is ineffective unless—
(a) it is made in writing, is contained in the
construction contract and confers power on the adjudicator to allocate his fees
and expenses as between the parties, or
(b) it is made in writing after the giving of
notice of intention to refer the dispute to adjudication.”
Only time and the courts will
decide whether this new provision is sufficient to achieve that which it was,
apparently, originally intended to address. For example, it may be possible to
successfully argue a variation upon the theme that a contractual term which
provides,
‘that whilst the adjudicator is empowered to allocate his fees and expenses as between
the parties, the Referring Party shall reimburse the Responding Party such sum
as the adjudicator may decide the Responding Party shall bear, or variations
upon such theme,’
is effective having apparently satisfied the requirements of the New s.108A.
Bloor Construction (UK) Ltd
v Bowmer & Kirkland (London) Ltd (2000) established that in the absence of
an express term to similar effect, there is an implied term in the adjudication
agreement that an adjudicator may correct accidental errors and omissions. The
New Act frames this provision in statute but sadly fails to take advantage of
the opportunity to clarify as to how long an adjudicator may have to make such
corrections. It is suggested that this is likely to be as circumstances
reasonably dictate./p>
The ability to take advantage of the slip rule however, remains limited to correcting clerical or
typographical errors. It is unlikely to extend to the correction of the
adjudicator’s factual, reasoning or judgement errors.
Whilst “paid when paid” remains banned under the Act, the insertion of s.110(1A) by the New Act broadly bans
“pay when certified” provisions from construction contracts except in those
circumstances in which the construction contract is an agreement for someone
else to execute the work and payment is conditional on that someone else doing
so, for example management contracts.
It likely therefore that Payers (i.e. the paying party) may seek to rely upon extended payment periods as a
consequence, in order to compensate for this change.
Due date not to be determined by notice
s.110 of the Act is also amended by the New Act, prohibiting the determination of the due date by
reference to a payment notice to be given by the Payer. Contravening clauses
will be ineffective and the relevant provisions of the Scheme will apply. This
demonstrates the need to have a “New Scheme” in place before the New Act may
come into force.
Payment notices under the Act have been changed so that under the new s.110A, a payment notice will have to be
given no later than 5 days after the payment due date. The construction
contract shall provide whether the Payer or Payee (i.e. the party to be paid for
services rendered) or Specified Person shall issue the notice. We anticipate
that the JCT standard suite of contracts shall provide for a Payer led payment
mechanism, as so to as it is expected that the revised Scheme for Construction
Contracts shall.
Payers will need to pay particular attention to the need to issue a payment notice even where the amount
due is thought to be zero, and include within it the basis on which that sum has
been calculated.
In circumstances of a Payer led payment mechanism and in the event that a Payer or a Specified Person fails to
issue a Payment Notice, the Payee may issue a “Default” Payment Notice pursuant
to s.110B. The Default Payment Notice may be given at any time after the
Payer’s Payment Notice should have been issued, but was not.
In the event of such a Default Payment Notice, the final date for payment is postponed by the number of days
after the due date that a Default Payment Notice is issued. Note however, that
a Default Payment Notice cannot be served if the Payee is to serve the payment
notice under the contract.
Main Contractors commonly require Sub-Contractors to submit applications so that the same may be
considered as part of the Main Contractor’s overall valuation process with
regard to the Main Contract works. With the introduction of the New Act all
should be aware that if the Payee has already issued a Payment Notice
(e.g. a Sub-Contractor’s application for payment) before the date that the
Payer’s Notice was required to be issued either because the contract in question
requires or permits such, then under the New Act such shall be the Payee’s
“Default Payment Notice”.
Withholding notices replaced by “pay less” notices
Having the Payer under a Payer led payment mechanism failed to have issued a Payment Notice and having instead
received a Default Payment Notice, unless the Payer issues a “Pay Less Notice”
before the prescribed period before the final date for payment pursuant to the
new s.111, the Payer shall be obliged to pay the Default Payment Notice in full,
save for in the event of the Payee’s insolvency after the period for issue of
the notice has expired.
The “Pay Less Notice” must state the sum that the Payer believes is due on the date the notice is issued,
even if that is ‘Nil’, together with the basis upon which it has been
calculated.
A “Pay Less” Notice can only be served either after a Payment Notice or a Payment Default Notice has been
served.
Enhanced suspension rights
s.145 of the New Act introduces new features to s.112 of the Act which provides a useful tool against
defaulters. The Payee will now be able to suspend their obligations either in
whole (which those in the industry are used to), or in part. The Contractor/
Sub-Contractor could therefore simply suspend its obligation to execute
Variations/ Changes. Those who are forced to take such drastic action as to
suspend will also be entitled to be paid the reasonable costs and expenses
associated with the suspension together with an extension of time including time
necessary to remobilise.
The changes to s.112 of the Act should prove an even more effective method of securing payment.
Nigel Davies
February 2011
The information & opinions expressed in this
article are not necessarily comprehensive nor do they represent the trenchant
view of the author; in any event this article does not purport to offer
professional advice. This article has been prepared as a summary and is
intended for general guidance only. In the case of a specific problem,
it is recommended that professional advice be sought.